Skip to content
St George's and City have merged. Find out more.

At St George’s, we are working hard to improve student facilities and equipment.  

In 2022, we were successful in our bid for £5.8 million, awarded by the Office for Students (OfS) specifically to boost teaching facilities and equipment in higher education institutions. 

St George’s was one of only 47 UK Universities and Colleges to be awarded the maximum amount of £5.8 million per provider. 

This funding, alongside other investments including many made by St George’s itself, will be used to deliver an Education Transformation Project that will enhance our hands-on skills facilities, create new student study spaces and equip the campus for efficient digital learning and study.   

We are really excited to significantly enhance teaching, learning and the campus experience for our students and staff.  Follow along here and look out for the #BuildStGeorges hashtag on social media – we'll be posting our progress as we go along. 

We welcome your feedback, to get in touch, please have a look at our Get involved section.

The project will progress across a three-year period and include: 

News and updates

News items about improvements to student facilities and equipment will be added to this section as and when they are available.

Timeline

Year 1

Year 1 Project Timeline
TimeframeActivity
January 2023 New Clinical Practice Space opening
March 2023 to July 2025 Upgrades to WiFi network on campus
April 2023 New flexible student computer room opening (Level 1, Jenner Wing)
May 2023 Equipment upgrades and charging facilities for students in lecture theatres (B, C, G and Michael Heron)
May 2023 Refurbishment and upgrade of physiotherapy labs (Level 5, Hunter Wing)
TBC New anatomy facility opening
Year 2
Year 2 Project Timeline
TimeframeActivity
March 2023 to July 2025 Upgrades to WiFi network on campus
April 2023 to March 2025 Refurbishment and digital enhancements of teaching spaces and lecture theatres across campus (Phase 1)
October 2023 Refurbishment and upgrade of two 10 bed hospital setting simulation suite (Level 4, Hunter Wing)
October 2023 Creation of extended library space for collaborative learning and accessing online content for students
TBC Refurbishing and upgrade of Paramedic Simulation Suite
Year 3
Year 3 Project Timeline
TimeframeActivity
March 2023 to July 2025 Upgrades to WiFi network on campus
April 2023 to March 2025 Refurbishment and digital enhancements of teaching spaces and lecture theatres across campus (Phase 2) 
TBC Creation of new flexible spaces for clinical skills training (Level 4, Hunter Wing)
TBC Digital upgrade of the Radiography Treatment Planning Suite
TBC Design and creation of additional multi-purpose collaborative study spaces for students
Find a profileSearch by A-Z